Project Online ReST API get recently updated projects

Brass Contributor

Hello Everyone,

 

I want to filter a list of projects that are recently updated. Which project related property is useful in this? LastPublishedDate or LastSavedDate or any other property / criteria?

 

Thanks & Regards,

Rohan

1 Reply

Hello @rohanw24, for the data in the following to APIs, the projects will need to be published to get updated:

You will find that the Saved / Modified dates match the published dates on these APIs apart from when a project summary publish happens. A project summary publish happens when you click Save from normal PDPs (not the Schedule PDP tasks ribbon). In that scenario you will find the modified / saved dates are later than the Published dates.

Paul