Hi
I hope someone can help
I am having an issue when uploading a new project from the desktop to project online.
The main base calendar for the system does not have any exceptions, as we are a global company and projects arent limited to one region it has been decided that we should ask the project managers to manually review national holiday exceptions and manually push tasks out rather than building the system to cover all potential holidays.
As is always the case, the issue I am having is a project which is an exception to the above rule. The project in question has a different base calendar which accounts for national holidays in one region. As this is a one off, and the project is very detailed and old, I would like to just upload it as is.
So:
The above ensures no tasks are assigned during the exemption period, Ive checked at each stage of the wizard and this approach is working
Then it goes wrong, as soon as you select save (in the wizard) the task dates all move so some are scheduled where there should be an exception i.e. it seems to adopt the standard base calendar, this is for tasks with and without resources assigned. The region specific calendar is still displaying in the working time box so I am not sure what is going wrong
Id be grateful if someone could help with this
Thanks
Matt
Nov 08 2022 12:28 PM
Nov 09 2022 06:06 AM
Hi Dale
Thanks for the swift reply
I didnt check out the resources, only changed it in the resource step of the upload wizard.
If I change it in the online resource it will change all other projects they are assigned to wont it? As this is a one off is there a way to upload but to only use the project calendar rather than the resource calendar?
Thanks for your help
Matt
Nov 09 2022 06:11 AM
Nov 11 2022 12:44 AM
Hi @Dale Howard
OK thank you.
Is there a way round this then? Id actually prefer the system to always take the project / work hours calendar over the resources calendar when we upload. So happy to change a setting to make this happen as a permanent thing if its possible
Thanks
Matt