Feb 02 2023 10:38 AM - edited Feb 03 2023 05:54 AM
Hello,
I am completely brand new to Project and am starting off with Plan 1 (found here) to get a feel for it. My main need from a project management tool, is to be able to create tasks that are hourly-based. Not just a whole day.
Is there a way to change the timeline to reflect hourly options? I see that I can set duration, but that doesn't affect the way the project looks on the Gantt chart.
Feb 02 2023 12:16 PM
Feb 03 2023 05:53 AM
Feb 03 2023 05:55 AM
Feb 03 2023 06:38 AM - edited Feb 03 2023 07:08 AM
dslusser --
If you need to plan your project tasks in hours and then to display those tasks in hours in the Gantt Chart view, then yes, the Project Plan 3 option will provide you with the Microsoft Project desktop version. In the Gantt Chart view, you will be able to zoom the timescale to show the schedule of tasks in hours and not in days. Hope this helps.
Feb 08 2023 08:15 AM