Project online essentials supporting subprojects?

David Jennings
New Contributor

As per the subject really, does Project Online Essentials support subprojects?

 

thanks

Dave

 

2 Replies
Highlighted

Just to confirm this is the feature required, I don't know if it is only in Project On premise?

 

https://support.office.com/en-gb/article/Plans-within-plans-master-projects-and-subprojects-35b02e56...

 

Hi David, Project Essentials is to be used by people in the team member role. To manage projects you need at least the Project Professional subscription. This also allows to manage subprojects in the web. To setup master and sub projects you always need the Project desktop client.
Related Conversations
Reporting on Project Online (PWA) Timesheets
Andy Dennis in Project on
3 Replies
Add, Edit, Delete Project Online data using Excel
MonteStJohns in Project on
5 Replies
Migrate from Project Server 2013 to Project Online
Adullah_Ismail in Project on
1 Replies
Project Online %work and actual cost ERROR
JeanLouis in Project on
2 Replies
CSOM throwing random error
Germán Torres in Project on
2 Replies