Jul 28 2021 02:20 AM
Hello together - wish you all a happy day ! Hopes you can help me.
We use MS Project Online (Plan5) with client Project Prof. 2016
Problem:
I manage multible projects at the same time, when I enter a resource and a resource conflict is displayes, I switch to Team Planner to view it.
If the conflict is with another project, I have to double-click on the task, then I get the project name, but not the task name.
Is it possible to display the name of the task?
Best
Jürgen Prechtl
Jul 29 2021 01:22 AM
If the other project is not opened, you cannot see the task name but only the project name. This is a security matter, the project manager of a project might not have the right to access any other projects. You'll note this is the same behavior in the resource usage view. For a give resource, you can see his assignment on the open project at task level, but the assignments on other projects are at project level.