Project Online CSOM: Get Assignment work per day plan

Occasional Contributor

Hi,

 

I have created a simple CSOM Application in VB.NET and i am able to view the assignments are assigned to Resource.

i have used following code to get Assignments for a resource:

 Dim entResUid As Guid = New Guid(ListView3.SelectedItems.Item(0).SubItems(0).Text)
 projContext.Load(projContext.EnterpriseResources.GetByGuid(entResUid))
 projContext.ExecuteQuery()

 Dim ResourceOne = projContext.EnterpriseResources.GetByGuid(entResUid)

 Dim ResAssignment = projContext.EnterpriseResources.GetByGuid(entResUid).Assignments
 projContext.Load(ResAssignment)
 projContext.ExecuteQuery()

 

the code is working fine,  for example i got the "Work" for a single assignment as 20hours.

 

But i need the work allocated per day says FirstDay 8 hrs, SecondDay 8hrs and third day 4 hrs

 

Is possible to get the work allocated per day instead of total work for assignment in CSOM.

 

please help me to get output

 

Thanks

1 Reply

@TJTalha Have you tried using AssignmentTimephasedDataset table?