We have recently begun using Project for the Web and frankly, it has been great. It has made a big difference, however, there is one small snag. As an IT company, we often work on a weekend, but it appears we cannot schedule work for Saturday or Sunday in Project for the Web. All the information I can find to set up the workdays on a project refer to Project Desktop client, but nothing for Project for the Web.
We get the following error 'Task start moved to the next working day' and it reschedules to the next working day.
I have attached a small video showing the issue. I would appreciate any pointers you may have for being able to set a task to be worked on a weekend.
Thank you
Leigh
Apr 30 2021 11:01 AM
Apr 30 2021 12:04 PM
Apr 30 2021 12:20 PM
@Dale Howard Thanks for the info. As you already understand that's not an option for most users and huge oversite. Each "tier" of project should have some overlapping functionality. The web version should include weekends and the full project should be able to filter them out if desired.