Hello,
We're able to add custom fields to Project Tasks table in the Project for the Web, which is a great feature.
However, according to this documentation (https://support.microsoft.com/en-us/office/create-a-custom-field-in-project-839d206f-b314-48f5-aa06-...), it says
"To reuse custom fields [in Project for the Web], create a copy of the project. Custom fields can't currently be used across projects or for PowerBI reports."
It appears we aren't able to use Custom fields for PowerBI Reports.
Are there any workarounds for this? Coding, API, power automate, or anything?
Is there anything scheduled in product roadmap to make this feature available?
Thanks,
Adil
May 04 2022 10:25 AM
Hello @Adil365 ,
Unfortunately these custom fields you create here:
Are not available for reporting, they are only available in the Project for the web interface.
Paul
May 05 2022 07:35 AM
May 06 2022 01:37 AM
@Duncan_Griffin are labels available to be seein in power bi reporting? How do I add these into my power bi models. I’m using project accelerator as a starting point for my project power bi reports.
May 06 2022 01:52 AM
Yes @ndrogo- they can be added to Power BI, you will need to update your Power BI Report to include those tables in the data model. At the end of this blog post I detail the tables you will need to include:
Paul
May 06 2022 02:09 AM
@Paul Mather Thank you this is perfect.
May 06 2022 05:54 AM - edited May 06 2022 05:57 AM
Thanks for this Could you offer any help on what the relationships should be for the Project Labels and Project Task To Label with the other tables and Task. I'm having trouble with the joins
May 08 2022 02:47 PM
Hello @ndrogo- ,
This blog post will help: https://pwmather.wordpress.com/2022/05/08/update-the-projectfortheweb-powerbi-template-to-include-ne...
Paul
May 18 2022 06:46 AM
@Paul Mather I'm having some issues with the relationships. I brought in the label data but when I add it to one of my grids in a report I get a error. Any advice see attached
May 18 2022 08:14 AM
Hello @ndrogo- ,
What is different to your Power BI data model compared to the steps outlined in the blog post? You could also download this template I created: https://github.com/pwmather/Project-for-the-web-Power-BI-Template/blob/main/Microsoft%20Project%20fo...
Paul
May 18 2022 08:16 AM
@Paul Mather Hi Paul, no difference I used the default template from MS. Let me check out your template and see if that helps Thanks,
May 18 2022 08:42 AM
@Paul Mather Hi Paul I downloaded the temple and tried to add the label to the task overview and got a similar error in in the template as my model. What I'm trying to do is add the label at the tasks.
Nick
May 18 2022 08:45 AM
Hello @ndrogo- ,
Does the new labels report page in the template show you the label data from your instance?
Paul
May 18 2022 08:51 AM
@Paul Mather Yes it does show on the labels report page
May 18 2022 10:07 AM
That's great to hear @ndrogo-
May 18 2022 11:02 AM
@Paul Mather yes however if I want to add Bookable resource of the task and start and finish it errors out. What relationship should I build to correct this?
May 23 2022 03:56 AM
@Paul Mather hi Paul any advice how to include label on task and book able resource? Every time I try to add task owner and label I get a error in the visual.
Jun 03 2022 03:33 AM
@Paul Mather Hi Paul sorry to be a pain.
h any advice how to include label on task and bookable resource? Every time I try to add task owner and label I get a error in the visual.
Jun 03 2022 08:12 AM
Hello @ndrogo- ,
No worries. You will just need to ensure the data model is updated to support the relationships between those other tables.
Paul
Aug 01 2022 03:07 PM
Hi @Paul Mather , thanks for your thorough instructions on adding Labels and Checklists to the Powerbi template, it was an immense help! Quick question, do you know if its possible for a powerbi visualization to refer to the color associated with a label? For example, have the colors of the slices of a pie chart map directly to the msdyn_colorindex or msdyn_colorindex_display values. Thanks again for posting the powerbi/project documentation!