Project for the Web - msdyn_projects statuscode

Copper Contributor

Hi there

 

I am troubleshooting a filtering issue on our P4TW Power BI Project report.

 

Issue concerns the field statuscode from table msdyn_projects. 

 

What does this field represent? Values I see are 1, 2 and 192350002 (which I find quite strange).

 

Is 1 for active and 2 for deactivated projects?

 

Thanks!

3 Replies
best response confirmed by Dave_the_Automator (Copper Contributor)
Solution

@Dave_the_Automator - Listed below are the values for the statuscode field.  It would be extremely helpful if Microsoft would publish schema documentation.

 

  • 1 = Active
  • 2 = Inactive - Sets project to read only
  • 192350000 = Closed - Set projects to read only and cancel future bookings
Excellent, thanks so much!
Glad to help. Let me know if you have any other P4W schema questions as I have quite of bit of time invested in developing our data model.
1 best response

Accepted Solutions
best response confirmed by Dave_the_Automator (Copper Contributor)
Solution

@Dave_the_Automator - Listed below are the values for the statuscode field.  It would be extremely helpful if Microsoft would publish schema documentation.

 

  • 1 = Active
  • 2 = Inactive - Sets project to read only
  • 192350000 = Closed - Set projects to read only and cancel future bookings