I´m still trying to learn Project for the web. One basic question that I can´t find a way how too do
How can I add a cost for each row (task) in my gantt-chart? Either in the web or in the powerapp layout, both works fine.
Thanks!
Jan 04 2021 02:08 PM
Solution@chris1265 --
As it currently exists, there is no Cost model associated with projects created in Project for the Web. Perhaps Microsoft will add some type of costing functionality in the future, but there is no such costing functionality in the tool today. Sorry, but hope this helps.