Project for the web - Dependencies

Copper Contributor

I would like to know if there are any tips to choose for a task "earliest start or latest finish" with the advance dependencies ? I don't know who to make a complex retor schedule without ""earliest start or latest finish"). Thank you for your help.

1 Reply
Kvin700 --

In Project for the Web, all tasks are scheduled with an As Soon As Possible constraint. As the software currently exists, there are no other available constraint types. Dependencies have nothing to do with the need you describe, by the way. Hope this helps.