I am looking into moving from Project Online to Project for the Web. Critical items for us are resource scheduling and project baselines. I have a solution for baselines, but I am struggling with using Bookings to get resources in place. It appears I might not be properly licensed (at least that is what the Ops team thinks), but the documentation I have read keeps telling me that a Project P5 license should grant me the ability to request and assign resources. When I try to save a resource request I get an insufficient permissions error:
Anyone have any details on what is needed or what I might need to get setup?
Dec 14 2022 07:06 AM
@BamDastard did this ever get resolved I'm having this issue now.
Dec 15 2022 10:42 AM
SolutionDec 19 2022 11:26 AM
Dec 15 2022 10:42 AM
Solution