Project for the Web - Allow Team members to edit/view only his task

Copper Contributor

Hello,

 

Project for the web - I created a project and create a security group for projects. added the team members.

 

Assign the task to teams. Now only task owner should able to edit the percentage complete for the task. 

 

Kindly Suggest 

15 Replies

Hello @sonika755 ,

Unfortunately this isn't possible, once the user has edit access to the project via the M365 Group - they can edit all tasks as you have seen. 

Paul

Thanks Paul for your reply. How the project manager will control the project plan. Example team member can delete the project task and other owner can update the task for another users. can you please suggest.

Hello @sonika755 ,

Unfortunately there is nothing out of the box. You could customise it though with custom code. Here is an example of preventing users deleting the project: https://techcommunity.microsoft.com/t5/project-blog/how-to-prevent-a-team-member-from-deleting-a-pro... 

Paul

Hi Paul, I am having issues with giving access to people on the Teams that are assigned to the Project for the Web. They can only edit the % Complete and check or uncheck that they are complete. How can the assigned member change dates on their tasks?
mylogi88 --

Pardon me for bumping into this thread. Because of time zone differences, Paul's work day may have already ended.

To answer your question, team members are only allowed to edit the % Complete value and to mark their tasks as completed. This is by design. Hope this helps.

@Dale_HowardMVP I created a project tab in a test team, added a couple of test tasks, and assigned them to two different team members.  The team members are able to see the tabs and the tasks, but they cannot even click on the task as "done" or change the % completed.  Everything is Read Only. What determines if a member has permission to check the task off as completed?

Sasan --

If the team members have a Project Plan 1 license, they will be able to edit the % Complete value and mark their tasks as completed. Without the Project Plan 1 license, all they can do is to view the project Read-Only. Hope this helps.

Hello @Sasan Baharaeen ,

For a user to be able to modify a project in Project for the web, the users will need one of the Project Plan licenses or Office 365 users with one of the defined licenses that allow limited edit access, details on the link below: 

https://learn.microsoft.com/en-us/project-for-the-web/office-365-user-view-access-to-project-and-roa...

You'll notice users with just E1, F1 etc. will get view only access.

Hope that helps

Paul

@Paul Mather Yes.  I figured out that users with Office 365 E1 license have view only access while users with Office 365 E3 license can edit project completion status and percent completed.

 

Thank you very much Paul.

@Paul Mather I have the Office 365 E3 and Project Plan 3. I created a task in Project for the Web and assigned it to myself and I did not see that this task shows up in "Assigned to me" in Planner. What else should I or the IT admin do to make this work. I am doing this test before I assign tasks to my team members and I was expecting this should work for myself as an assignee.
Thanks,
Tingjun

Hi @Dale_HowardMVP ,

Our organization have Project plan 3 in addition to Microsoft 365 E5. At the moment all the team members see Limited Access next to the Project name . Is there a possibility to provide team members of Project access to edit tasks wherein they can add tasks and upload attachments? Currently thy can only update %completion.

Please let us know if there is a workaround that can be used.

 

Otherwise all these edit and upload has to go through only one person that can create a bottleneck.

 

ProjMgrSA --

Unless I am totally misunderstanding the default permissions in Project for the Web, only the designated project manager can edit the project. Team members, regardless of whether they have a Project Plan 1 or Project Plan 3 license, can only update % Complete and mark tasks as completed. This is just how the software works, at least for the moment. Sorry, but hope this helps.
best response confirmed by Dale_HowardMVP (MVP)
Solution
Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.

We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
RFromm --

OUCH! Thanks for jumping into this thread. Truth be known, I do not spend much time nowadays, given the fact that most of my work is with the Microsoft Project desktop application, Project Online, and Project Server. You insight was helpful. Thanks for sharing.
1 best response

Accepted Solutions
best response confirmed by Dale_HowardMVP (MVP)
Solution
Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.

We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.

View solution in original post