SOLVED

Project Center Default View Deleted so now Project Center doesn't load for users

%3CLINGO-SUB%20id%3D%22lingo-sub-1829651%22%20slang%3D%22en-US%22%3EProject%20Center%20Default%20View%20Deleted%20so%20now%20Project%20Center%20doesn't%20load%20for%20users%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1829651%22%20slang%3D%22en-US%22%3E%3CP%3EProject%20Center%20Default%20view%20was%20deleted%20by%20mistake%2C%20so%20now%20Project%20Center%20doesn't%20load%20for%20users.%20However%20as%20Site%20Collection%20Admin%20I%20am%20the%20only%20one%20who%20can%20see%20all%20the%20new%20views%20created%2C%20and%20don't%20get%20the%20%22Loading%22%20message%20in%20the%20view%20iFrame.%20Also%20the%20users%20have%20the%20%22project%22%20banner%20%22greyed%20out%22.%20I%20have%20everything%20working%20well%20...%3C%2FP%3E%3CP%3EI%20can't%20find%20any%20solution%20to%20this%20on%20the%20forums.%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-1829862%22%20slang%3D%22en-US%22%3ERe%3A%20Project%20Center%20Default%20View%20Deleted%20so%20now%20Project%20Center%20doesn't%20load%20for%20users%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1829862%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F134086%22%20target%3D%22_blank%22%3E%40Rosalia%20Dias%3C%2FA%3E%26nbsp%3B%2C%3C%2FP%3E%0A%3CP%3EAre%20you%20using%20Project%20Server%20on-premises%20or%20Project%20Online%20in%20Office%20365%3F%20If%20you%20are%20using%20Project%20Server%20on-premises%2C%20which%20version%20is%20this%202013%2C%202016%20or%202019%3F%20In%20Project%20Server%202013%20this%20used%20to%20work%20so%20might%20be%20worth%20a%20try%3A%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Fpwmather.wordpress.com%2F2013%2F11%2F20%2Fprojectserver-2013-project-center-view-failed-to-load-ps2013-sp2013%2F%22%20target%3D%22_blank%22%20rel%3D%22noopener%20nofollow%20noreferrer%22%3Ehttps%3A%2F%2Fpwmather.wordpress.com%2F2013%2F11%2F20%2Fprojectserver-2013-project-center-view-failed-to-load-ps2013-sp2013%2F%3C%2FA%3E%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-1829866%22%20slang%3D%22en-US%22%3ERe%3A%20Project%20Center%20Default%20View%20Deleted%20so%20now%20Project%20Center%20doesn't%20load%20for%20users%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1829866%22%20slang%3D%22en-US%22%3E%3CP%3E%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F8793%22%20target%3D%22_blank%22%3E%40Paul%20Mather%3C%2FA%3E%26nbsp%3BI%20am%20using%20Project%20Online%20...%20O365%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

Project Center Default view was deleted by mistake, so now Project Center doesn't load for users. However as Site Collection Admin I am the only one who can see all the new views created, and don't get the "Loading" message in the view iFrame. Also the users have the "project" banner "greyed out". I have everything working well ...

I can't find any solution to this on the forums.

5 Replies

Hello @Rosalia Dias ,

Are you using Project Server on-premises or Project Online in Office 365? If you are using Project Server on-premises, which version is this 2013, 2016 or 2019? In Project Server 2013 this used to work so might be worth a try: https://pwmather.wordpress.com/2013/11/20/projectserver-2013-project-center-view-failed-to-load-ps20...

Paul

@Paul Mather I am using Project Online ... O365

@Rosalia Dias OK - did the suggestion at the end of the blog post work for you? If not, you might need to open a support ticket via your Office 365 tenant so that Microsoft can fix this for you.

Paul

@Paul Mather Hi thanks for trying to help, I really appreciate it! Unfortunately we can't use the suggestion in your blog because the "Project" banner is greyed out for the users so they can't change view. I have opened a support ticket, and will post solution they provide (hopefully!) here so can be shared to community. 

Cheers,

Rosie

 

best response confirmed by Rosalia Dias (Occasional Contributor)
Solution

@Paul Mather the problem was in fact that a default view was deleted, as no easy and quick way around this I rebuilt the site from scratch and WILL NEVER DELETE ANY DEFAULT views, fields etc. from our PWA environments ever again!