Sep 19 2023 11:53 AM
Can anyone help me figure out what would cause this?
Bar Configuration before turning OFF round to whole days
and after turning off round to whole days
I changed nothing other than unchecking the radio box for rounding in the layout menu.
Sep 20 2023 08:42 AM
Sep 20 2023 01:19 PM
Sep 20 2023 02:03 PM
Sep 20 2023 03:10 PM - edited Sep 20 2023 03:11 PM
Maybe use "Baseline Estimated Finish" instead of "Baseline Finish". It worked for me.
After Rounding of Bars to Whole Days
Before Rounding of Bars to Whole Days
=jerome