Jan 08 2023 02:46 AM
i want to set captions on the timeline like in this Image
I cant find the way to do so .
Please Help
Jan 09 2023 07:42 AM
Hello @orenmedasystech ,
These are the tasks names from the source tasks / projects, if I've understand the question correctly.
Paul
Jan 09 2023 11:05 PM
yes you have understood correctly I want the name of the task to appear in the time line like in the screen shot that I attached @Paul Mather
Jan 10 2023 12:43 AM
SolutionHello @orenmedasystech ,
That happens by default if the task duration is long enough - so that the bar is large enough to render the task name:
Paul
Jan 12 2023 06:53 AM
Hi Paul and thank you for the answer . but as you can see the name of the task is very short and the time line is long but it does not show the name on the Bar.
Jan 12 2023 07:58 AM
Hello @orenmedasystech ,
That is a different app - the app you sent a screenshot for in the original post was the Roadmap app. The screenshot above is the Project for the web app, that does not show the task name on the task bar.
Paul
Jan 15 2023 11:44 PM
Jan 10 2023 12:43 AM
SolutionHello @orenmedasystech ,
That happens by default if the task duration is long enough - so that the bar is large enough to render the task name:
Paul