SOLVED

project 4 the web how to add caption on the timeline

Copper Contributor

i want to set captions on the timeline like in this Image 

I cant find the way to do so .

 Please Help 

orenmedasystech_0-1673174680017.png

 

6 Replies

Hello @orenmedasystech ,

These are the tasks names from the source tasks / projects, if I've understand the question correctly.

Paul

yes you have understood correctly I want the name of the task to appear in the time line like in the screen shot that I attached @Paul Mather 

best response confirmed by Dale Howard (MVP)
Solution

Hello @orenmedasystech ,

That happens by default if the task duration is long enough - so that the bar is large enough to render the task name:

PaulMather_0-1673340184407.png

Paul

 

@Paul Mather 

 

orenmedasystech_0-1673535066008.png

Hi Paul and thank you for the answer . but as you can see  the name of the task is very short and the time line is long but it does not show the name on the Bar.

 

Hello @orenmedasystech ,

That is a different app - the app you sent a screenshot for in the original post was the Roadmap app. The screenshot above is the Project for the web app, that does not show the task name on the task bar.
Paul

O.K Thank you for your answer it's helped A lot .
1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution

Hello @orenmedasystech ,

That happens by default if the task duration is long enough - so that the bar is large enough to render the task name:

PaulMather_0-1673340184407.png

Paul

 

View solution in original post