Project 365 - how do I create a baseline?

Copper Contributor

Hi.  I have Project Professional installed on my computer but I'm trying to switch over to Project 365.  I don't see any option on 365 to create a baseline however.  Any suggestions?

1 Reply
best response confirmed by Dale Howard (MVP)
Solution

@MaxBorenstein Project 365? If you meant Project for the Web, project level baselines are rolling out starting this month https://www.microsoft.com/en-us/microsoft-365/roadmap?featureid=187139

They plan to provide more detailed, task/assignment level baselines in the future.