May 22 2022 09:01 PM
Hi,
I have a bunch of tasks, which are linked to a set of key deliverables. A set of key deliverables must be met to meet a milestone.
Is there a way to show the progress towards a milestone as and when key deliverables are met ?
One way, I could think was to have a a summary task of key deliverables, and mark this summary task as milestones, but there are few issues
1. Having a milestone with non-zero duration is counter intuitive
2. If there are multiple milestones, the summary task method will require nesting of milestones & deliverables.
Is there an easier way, where deliverables are linked to the milestone to which they align to and as these deliverables are met, the milestone to which they are linked shows a progress % . Is there a way to represent this abstraction visually say in the gantt chart or timeline view - Milestones are shown as diamond in these views, so progress made to achieve the milestone can't be shown by default as such.
Any thoughts ??
May 23 2022 05:45 AM
May 23 2022 06:37 AM
May 24 2022 05:28 AM
May 24 2022 11:55 AM
Refer to the screenshot below for what your project should look like. See how this project has summary tasks and a milestone for each summary task? And notice the % Complete value to the right of each summary task's Gantt bar? That is the approach I am recommending for you. Hope this helps.