Hi team
I want a number of people to automatically have access to a project's project site in POL. I have POL permissions set. But I don't know how to set up these permissions in the project site template. It only has SP permissions and this breaks when a new project is created.
Any help gratefully received.
Many thanks
James
Jun 04 2021 06:55 AM
SolutionJun 04 2021 08:27 AM
Hi @James_Price ,
To add to @Dale Howard's advice, you will also needs to ensure the Enterprise Project Types (EPT) are set to sync the user permissions:
PWA Settings > Enterprise Project Types > Click an EPT > Scroll to the "Synchronization" section, ensure the "Sync User Permissions" is enabled > Click Save. Repeat for other EPTs. Then publish the projects for the permission sync job to run.
Paul