PPM Best Practice for Putting Project "On Hold"? Looking for Suggestions.

%3CLINGO-SUB%20id%3D%22lingo-sub-177050%22%20slang%3D%22en-US%22%3EPPM%20Best%20Practice%20for%20Putting%20Project%20%22On%20Hold%22%3F%20Looking%20for%20Suggestions.%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-177050%22%20slang%3D%22en-US%22%3E%3CP%3EIn%20Microsoft%20PPM%2FProject%20Online%2C%20I'm%20interested%20to%20know%20how%26nbsp%3Bothers%20are%20handling%20for%20putting%20a%20project%20%22On%20Hold%22.%20Do%20you%20have%20different%20workflow%20phases%2Fstages%3F%20Do%20you%20have%20status%20indicator%20colors%20that%20indicate%20a%20project%20is%20on-hold%3F%20Do%20you%20have%20an%20enterprise%20project%20custom%20field%20that%20indicates%20this%3F%20I'd%20love%20to%20hear%20what%20others%20are%20doing%20and%20if%20you've%20run%20across%20any%20other%20good%20resources%2C%20posts%2C%20etc.%20that%20discuss%20this%20topic.%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-180709%22%20slang%3D%22en-US%22%3ERe%3A%20PPM%20Best%20Practice%20for%20Putting%20Project%20%22On%20Hold%22%3F%20Looking%20for%20Suggestions.%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-180709%22%20slang%3D%22en-US%22%3E%3CP%3EJust%20the%20normal%20%22status%22%20field%20we%20have%20for%20other%20reasons%20like%20%22ready%2C%20planning%2C%20in%20progress%2C%20testing%2C%20etc%22.%20Another%20one%20says%20%22hold%22.%20Along%20with%20that%20we%20either%20delete%20or%20push%20out%20the%20planned%20work%20so%20as%20not%20to%20affect%20resource%20capacity.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EWe%20also%20keep%20on%20hold%20projects%20visible.%20Having%20it%20present%20means%20someone%20has%20to%20do%20something...%20get%20it%20started%20again%2C%20formally%20cancel%20it%2C%20what%20have%20you.%20Cancelling%20or%20completing%20is%20what%20makes%20the%20projects%20come%20off%20of%20most%20of%20our%20views.%3C%2FP%3E%3C%2FLINGO-BODY%3E
Highlighted
Kristina Benoit
Established Member

In Microsoft PPM/Project Online, I'm interested to know how others are handling for putting a project "On Hold". Do you have different workflow phases/stages? Do you have status indicator colors that indicate a project is on-hold? Do you have an enterprise project custom field that indicates this? I'd love to hear what others are doing and if you've run across any other good resources, posts, etc. that discuss this topic.

1 Reply
Highlighted

Just the normal "status" field we have for other reasons like "ready, planning, in progress, testing, etc". Another one says "hold". Along with that we either delete or push out the planned work so as not to affect resource capacity.

 

We also keep on hold projects visible. Having it present means someone has to do something... get it started again, formally cancel it, what have you. Cancelling or completing is what makes the projects come off of most of our views.

Related Conversations
Problem when creating a recurrence pattern
Hienbh2203 in Project on
0 Replies
Project Timesheet Submission via Smart Phone hitting issues
Kurran in Project on
0 Replies
API access to the new Project Online
BenjaminMel in Project on
2 Replies
Problems Editting Enterprise Calendars
DeanS50 in Project on
3 Replies
Last Log In Activity on Microsoft Project?
Devryk in Project on
0 Replies