Power BI is Pulling 4 sets of baseline data from PWA

Copper Contributor

Hi All,

 

I am having an issue with PWA integration, the connection is setup and working correctly so far but looking closer at the data I have 4 versions of the data coming into BI desktop:

Screenshot 2023-10-30 123440.png

 

You can see from the above screenshot that baseline number 0 for the same project name has 4 sets of data and this is causing massive confusion issues in Power BI.

 

Any ideas why this is happening please?

 

Thanks

 

Phil

 

2 Replies

Hello @Pcd2h ,

It looks like that is the baseline data for 4 different tasks looking at task IDs.

Paul

@Paul Mather 

Hi Paul,

 

It may look like that but when reviewing the rest of the rows the task name and other attributes are the same, causing me issues in my power BI data.