SOLVED

Portfolio Management using Project and PowerBI

New Contributor

I have several projects being tracked in Project for the Web. The user interface is great and I have a lot of buy-in from my sponsors and project teams. 

 

However, I would like to create a single dashboard view of all our projects, probably in PowerBI, for upper management. Has anyone been able to do this? Are there examples, use case studies, demos, or videos about modern project management portfolio solutions? 

 

I don't want to have to re-input data that's already being kept up-to-date in Project.

Thanks!

2 Replies
best response confirmed by Llysight (New Contributor)
Solution

Hello @Llysight ,

Have you tried the Project for the web Power BI template from Microsoft? See details here if you haven't: https://github.com/OfficeDev/Project-Power-BI-Templates/tree/master/Project%20for%20the%20Web 

Details on extending the template here: https://support.microsoft.com/en-us/office/extend-the-power-bi-template-for-project-for-the-web-23fb... 

Hope that helps 

Paul

This looks like a great starting point, thanks!