SOLVED

POL permissions: If a resource have Team Member permission for a project even if they are a PM...

Brass Contributor

Hi Team

Is it possible for a resource to have team member permissions for one project even though they have project manager permissions in the resource centre? 

 

Many thanks 

James 

3 Replies
best response confirmed by James_Price (Brass Contributor)
Solution
James -- In theory, the answer is yes, but it all depends on how your application administrator configured configured the Project Managers security group. In essence, the Project Managers security group would need to be configured so that members of the group only have access to their own projects and cannot see or access any other project. The resources in question would need to be members of both the Project Managers and Team Members security groups. Hope this helps.
James -- You are more than welcome for the help, my friend!
1 best response

Accepted Solutions
best response confirmed by James_Price (Brass Contributor)
Solution
James -- In theory, the answer is yes, but it all depends on how your application administrator configured configured the Project Managers security group. In essence, the Project Managers security group would need to be configured so that members of the group only have access to their own projects and cannot see or access any other project. The resources in question would need to be members of both the Project Managers and Team Members security groups. Hope this helps.

View solution in original post