SOLVED

POL: Manager to view certain projects...

Contributor

Hi team 

I'm using POL.  I'd like a manager to view projects they are working on but not the others (similar to a PM).  Can someone give me instructions on how to do this as I'm struggling.

Many thanks 
James 

3 Replies
best response confirmed by Jamesp435 (Contributor)
Solution
James --

Add the manager to the default Team Members group. The PMs of the relevant projects simply need to add this manager as a team member in these projects and then to publish them. By taking these steps, the manager will be able to see his/her projects in the Project Center page in PWA. Hope this helps.
Nice one. Thanks for this Dale
James
You are more than welcome for the help, my friend! :)