Jan 23 2024 12:57 AM
Hi team
I've want to change a project's site template. I've gone into Pwa settings and removed it but when I add the template again it's adding the wrong site template. Can someone help me with either easily changing the site template somehow or tell me how I can change the default site template when adding using 'Connected SP sites'.
Many thanks for this
James
Jan 23 2024 04:39 AM
Hi @James_Price ,
The site template is set on the EPT. Update it on the EPT/s:
Then new project sites created after that update to the EPT/s will use the new template.
Paul
Jan 23 2024 06:53 AM
@Paul_Mather Thanks Paul, but how can I change the project site on an existing project? Many thanks
Mar 04 2024 01:56 AM
if you already deleted the existing project site for the project and then create a new site using the "Connected SharePoint Sites" menu the system always applies the template that is set in the Enterprise Project Type settings as Paul pointed out.
So, if you want to change the template, you need to conduct the following steps:
Otherwise, you could create a new SharePoint site using the template you want and then use the URL in the "Connected SharePoint Sites" menu via the "Edit site address" button.