Planning activity in different days

Copper Contributor

Hello! I'm new here and I have one question about planning activity in Microsoft Project. For example the activity start on 01/09, the following day is on 05/09 and the end is on 25/09. How can I represent on Microsoft Project? Because if I write: start 01/09 and finish 25/09, the software counts 24 days..but this is not right because the duration is 3 days. Someone can help me, please?

 

2 Replies
best response confirmed by Dado44 (Copper Contributor)
Solution

Hello @Dado44 ,

Are you looking to do something like this with split tasks

splittask.png

 

 

 

 

 

 

 

 

https://support.microsoft.com/en-us/office/split-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca

 

Paul

@Paul Mather thanks a lot!

1 best response

Accepted Solutions
best response confirmed by Dado44 (Copper Contributor)
Solution

Hello @Dado44 ,

Are you looking to do something like this with split tasks

splittask.png

 

 

 

 

 

 

 

 

https://support.microsoft.com/en-us/office/split-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca

 

Paul

View solution in original post