Overallocation picture only accurate with resource all projects open?

%3CLINGO-SUB%20id%3D%22lingo-sub-185376%22%20slang%3D%22en-US%22%3EOverallocation%20picture%20only%20accurate%20with%20resource%20all%20projects%20open%3F%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-185376%22%20slang%3D%22en-US%22%3E%3CP%3EI%20am%20experimenting%20with%20project%20online%20and%20the%20desktop%20software%20as%20a%20solution%20for%20project%2Fresource%20management%2C%20but%20I%20have%20hit%20some%20confusing%20problems%20in%20the%20program.%26nbsp%3B%20First%2C%20let%20me%20say%20the%20auto-scheduling%20based%20on%20resource%20availability%20is%20phenomenal%20when%20it%20works.%26nbsp%3B%20Notifications%20of%20over%20allocation%20and%20fixed%20external%20date%20problems%20are%20really%20great.%26nbsp%3B%20However%2C%26nbsp%3BI%20noticed%20that%20while%20the%20auto%20scheduler%2Fleveler%20will%20pick%20up%20on%20resource%20overallocation%20on%20multiple%20projects%20for%20a%20given%20resource%20assignment%20when%20those%20projects%20are%20open%2C%20it%26nbsp%3B%3CSTRONG%3Ecompletely%20ignores%3C%2FSTRONG%3E%20schedules%20and%20assignments%20for%20projects%20that%20are%20%3CSTRONG%3Enot%3C%2FSTRONG%3E%20directly%20open%20in%20the%20application.%26nbsp%3B%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EI%20must%20be%20missing%20something%20here%20because%20the%20auto%20scheduler%20overlapping%20task%20assignments%20without%20even%20indicating%20the%20other%20allocations%20almost%20makes%20the%20software%20useless%20from%20a%20resource%20management%20view.%26nbsp%3B%20To%20accurately%20schedule%20a%20project%20around%20other%20schedules%2Fassignments%20you%20would%20need%20to%20have%20open%20(and%20know)%20every%20project%20every%20resource%20is%20ever%20scheduled%20on!%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-185818%22%20slang%3D%22en-US%22%3ERe%3A%20Overallocation%20picture%20only%20accurate%20with%20resource%20all%20projects%20open%3F%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-185818%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20Myles%2C%3C%2FP%3E%3CP%3EYou%20need%20to%20check%20the%20%22Load%20Summary%20Resource%20Assignments%22%20option%20when%20starting%20the%20Project%20client.%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-left%22%20image-alt%3D%22LoadSummaryResources.png%22%20style%3D%22width%3A%20272px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F32787iDE131EF07F18AE37%2Fimage-size%2Flarge%3Fv%3D1.0%26amp%3Bpx%3D999%22%20title%3D%22LoadSummaryResources.png%22%20alt%3D%22LoadSummaryResources.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EIf%20you%20don't%20see%20it%2C%20be%20sure%20to%20activate%20the%20dialog%3A%3C%2FP%3E%3CP%3EFile-%26gt%3BInfo-%26gt%3BManage%20Accounts%3A%20Configure%20Accounts-%26gt%3BWhen%20Starting%3A%20%22Choose%20an%20account%22%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E
Contributor

I am experimenting with project online and the desktop software as a solution for project/resource management, but I have hit some confusing problems in the program.  First, let me say the auto-scheduling based on resource availability is phenomenal when it works.  Notifications of over allocation and fixed external date problems are really great.  However, I noticed that while the auto scheduler/leveler will pick up on resource overallocation on multiple projects for a given resource assignment when those projects are open, it completely ignores schedules and assignments for projects that are not directly open in the application.  

 

I must be missing something here because the auto scheduler overlapping task assignments without even indicating the other allocations almost makes the software useless from a resource management view.  To accurately schedule a project around other schedules/assignments you would need to have open (and know) every project every resource is ever scheduled on! 

 

 

1 Reply

Hi Myles,

You need to check the "Load Summary Resource Assignments" option when starting the Project client.

LoadSummaryResources.png

 

 

 

 

If you don't see it, be sure to activate the dialog:

File->Info->Manage Accounts: Configure Accounts->When Starting: "Choose an account"