Offline Project Plan - Missing Custom Field Values

Copper Contributor

When trying to work offline on a copy of our enterprise template, the Custom Fields are all available, but some fields are missing the values, as below.  

 

APS1979_0-1647538116294.png

 

Whereas if I open the same plan and connect to PS, with a plan saved locally, those field values appear. 

 

Can someone advise why values are present for some and not all, and if there's any way of saving a plan offline with all field values available?

 

2 Replies

Hello @APS1979 ,

I guess Gate is a look up table? The project client will need to be connected to the server (Project Online or Project Server) to populate that field and pick list - that is by design / a limitation. 

Paul

Hi Paul, correct. I feared that was the case but hoped I'd have been proven wrong! Thanks very much for confirming, least I know the limitations now.

Cheers again.