Someone know how to set up a new column to show me the number of assigned resources on tasks?
In column Tekst 1 i have drawn numbers in red just for an example.
And also i would like to have a column that converts hours into days.(column Tekst 2)
Mar 22 2022 09:08 AM
Mar 22 2022 09:12 AM
Mar 22 2022 10:27 AM
Mar 23 2022 01:06 AM
Mar 23 2022 08:52 AM
Mar 23 2022 07:04 PM
Mar 24 2022 02:25 AM
Mar 24 2022 08:44 AM
SolutionMar 25 2022 02:59 AM
Thanks again!
If you see the pic i posted here. Im standing in the Ganth view where i have my tasks.
I was hoping i could add recources form here, and i can, but these lists i have found dont show recources
that is free(not added to any tasks. I have 60 recources, so the list is painfully long.
I know i can go to another view and sort columns so the free recources will be in top. I was just hoping
i could stand in Ganth view, find tasks and from there easy get available recources so i can add.
I can see im terrible to explain
Mar 25 2022 08:22 AM
Mar 25 2022 09:26 AM
Apply the Resource Sheet view.
Add a number field (Number1 for example)
Customize the field and under Calculation for task and group summary rows: select Count all
Then apply a group by on the Group field.
Mar 25 2022 09:30 AM
Mar 25 2022 10:00 AM
Use a custom field Text and enter the formula in it
[Duration]/[Minutes Per Day] & " days"
and you are done.
Calculation is based on 8 hours per day as defined in project calendar, if you say 7.5 hours, it will change automatically.
Mar 25 2022 01:11 PM
Mar 25 2022 03:06 PM - edited Mar 25 2022 03:07 PM
MS Project is very sufficient tool to manage the project efficiently. No Macro needed.
I used task usage view instead of resource usage and get this. you can slice and dice the way you want to see it.
In the view "TASK: usage", Group the table after Assignment and then Name (resource-name) + check the box "group aggregation, not tasks"
Mar 25 2022 07:03 PM
Mar 25 2022 08:37 PM
Mar 25 2022 09:09 PM
Mar 26 2022 09:14 AM
Mar 24 2022 08:44 AM
Solution