New Feature available: Team resources replacable by multiple assignments (1:n replacement)

Steel Contributor

Hi all,

The user voice item "Allow multiple team resources to apply for a task that has been assigned to a team resource (allow 1:n replacement for team resources)" has been completed and rolled out to all tenants.

If you want to use the new functionality, you need to enable it first via "PWA Settings-->Task Settings and Defaults", see screenshot below.

 

User voice entry: https://microsoftproject.uservoice.com/forums/218133-microsoft-project/suggestions/11573715-allow-mu...

Fastrack Roadmap entry: https://fasttrack.microsoft.com/roadmap#R-59625

Enable 1:n team task featureEnable 1:n team task feature

 

 

 

 

 

 

 

 

 

 

 

 

0 Replies