May 27 2022 04:51 AM
Hi.
Using MS Project (Prof 2016)
I have several tasks with mixture of of some showing progress (% work complete).
The issue is that in the timeline view most of the tasks showing progress can be seen as having progress by being a different colour.
I have several tasks and added progress, but though i can see task in timeline view, it doesnt show the progress in a different share. I have tried deleting task and re-entering and same thing happens.
Need some help so that i can see progress in timeline view.
May 27 2022 08:05 AM
May 31 2022 12:51 AM
Thanks for replying.
here is screen shot. You can see Aspire lines 215, 216 dont show progress on timeline view
have adjusted percentages and retried deleting line and putting back in.
in the other workstreams it works fine.
May 31 2022 09:20 AM
May 31 2022 12:30 PM
Hi, should have done with better screen shot, hadnt realised these were not captured in screen shot.
How about this:
The summary task doesn't also change the percentage done, when i increase the work complete in the sub tasks. So must be something to do with the summary line. Have tried deleting the successors tasks and still no difference
Thanks P.
May 31 2022 12:57 PM
SolutionJun 01 2022 01:19 AM
Jun 01 2022 06:25 AM
May 31 2022 12:57 PM
Solution