MS Projects Team Planner

Copper Contributor

Hi

I use Projects to schedule in our work for the coming weeks/months mainly using the team planner option to visualize what each resource is working on. 

The issue I'm having is that if I add a resource to a current task, sometimes the duration doesn't reduce equally for each resource. All resources are set to the same calendar/days off etc. 

 

Any ideas with what I could be doing wromg? Example below

 

jakewaze_0-1643679570164.png

 

 

2 Replies
jakewaze,
Project will NOT balance the workload when you add another resource to an existing task. A similar post recently appeared on the Project Answers forum. You might want to take a look:
https://answers.microsoft.com/en-us/msoffice/forum/all/peak-units-recalculation/b360525d-931e-4b38-8...
John

@John-project 

Thanks John, I will have a read through.