I use Projects to schedule in our work for the coming weeks/months mainly using the team planner option to visualize what each resource is working on.
The issue I'm having is that if I add a resource to a current task, sometimes the duration doesn't reduce equally for each resource. All resources are set to the same calendar/days off etc.
Any ideas with what I could be doing wromg? Example below