Nov 30 2023 02:33 PM
I already have a project plan in MS Project and want to make it available in SharePoint, which i did, i selected it to sync with SharePoint however i have to sync it each and every time i close/open MS project using the App. Why have the sync there when its actually not working as intended? Having to re-sync manually each and every time is really horrible user experience and i dont want to open the project via browser using the app.
I have the file already in the SharePoint library and if i open it using the MS project app, i just want it to be able to Sync. If i have done the sync, it should be able to sync every time automatically.
To sync MS Project using App with SharePoint Task Web Part. To do that:
Steps mentioned above are the steps i have to take each and every time .... which is not ideal.
Hope this reaches the MS Project dev team and that they fix this issue.
Regards,
Mar 15 2024 05:01 AM
I also experience the issue mentioned above and will be following this thread for a response. Thanks! @theking021 for bringing this forward.
To my understanding, there might be a movement towards Project Operations on Dynamics 365 to replace Project Online. Is there any truth or supporting announcements regarding this possibility?