Jun 14 2021 06:53 PM
Hi team
In MS Project Gantt, when I tick on the 'Use fiscal year' box, the labels change to the previous year. And this is exactly what's happening in the Timeline view. The starting task is 8 Jan 2021, but the first label is Feb 20. However, in the Timeline view there is no 'Use fiscal year' box to untick.
Any ideas on what I can do?
Many thanks
James
Jun 15 2021 05:21 AM
SolutionJun 15 2021 07:31 PM
Jun 16 2021 11:02 PM
Jun 18 2021 05:20 AM
Jun 19 2021 09:51 PM
Jun 20 2021 12:53 PM - edited Jun 20 2021 01:06 PM
Dale already answered your question but he may not be on-line today so please allow me to make an observation. The months and years stated in your last posting do not match the screen shot posted. The screen shot shows Jan '21 through Apr '21 and then May 22' to Apr '22 for the Timeline view. The Gantt Chart timescale shows Jan '21 through Apr '22 as a "normal" year. That presentation is synonymous with Project > File > Options > Schedule tab set for a "fiscal year starts in" May and the Gantt Chart timescale option for "use fiscal year" unchecked.
No strange display behavior, just an inconsistency with fiscal year settings.
John
Jun 20 2021 07:04 PM
Jun 21 2021 07:43 AM
Aug 24 2021 08:33 PM
@John-project @James_Price I was having a similar issue where I had set the FY to be July but as I presented this became confusing to the audience and wanted to revert back to just a timeline view. There is No option to change the Timeline from financial year to just standard months. Just by taking the tick off does not reset this (Unless Starting month is January
To resolve this you need to take the tick off "Use starting year for FY Numbering" and reset the "Fiscal year starts in: January that removes the Fiscal year from appearing in the timeline and reverts back to standard months
Aug 24 2021 09:38 PM
@clinnd thanks for this. I think this was cover in Dale's response. It seems to do the trick.
Cheers
James