Mar 22 2023 02:27 AM
Hi Community
I have a Project where I need to apply weekend working.
I have created a new calendar where all dates are 'Working'
I then apply this calendar to the task and tick 'Scheduling ignores resources calendar'
However, I then go to update this task and it skips the weekends as if it was still using the 'Standard' calendar.
I just cant seem to work out what is going on?
Please help!
Mar 22 2023 05:24 AM
Mar 31 2023 12:30 AM
@Dale Howard apologies for the delayed response - I didn't seem to get a notification.
In answer to your points:
Do you have a resource assigned to this task? No, I don't have a resource assigned. Below is what I have:
No tasks have been progressed to 100% - Hope the below makes sense, this has never happened to me before so rather baffled!
1. The task date circled in red needs to be Sun 19/03/23
2. Calendar in Task Information is selected to 'Weekend Comms'
3. 'Weekend Comms' calendar has Sun 19/03/23 as a 'Working day' so why is it not changing?
Mar 31 2023 05:14 AM