Sep 14 2021 02:51 AM
Hi Expert,
Wonder if someone could assist ,me with something or perhaps point us in the right direction please?
I'm currently working on a Milestone Plan for reporting project work. I’ve built a project plan using MS project but I'm struggling with the logic to align the % complete to the status of the task.
Using an example below:
Start Date 1st April 2021
Target Finish Date 31st July 2021
Actual Finish Date not yet complete
Progress 80%
Task Status On Schedule
Start Date 1st April 2021
Target Finish Date 31st July 2021
Actual Finish Date 12th August 2021
Progress 100%
Task Status Late
Start Date 1st April 2021
Target Finish Date 31st July 2021
Actual Finish Date 15th July 2021
Progress 100%
Task Status Early Complete
Start Date 1st April 2021
Target Finish Date 31st October 2021
Actual Finish Date not yet complete
Progress 60%
Task Status Future Task
Start Date 1st April 2021
Target Finish Date 31st October 2021
Actual Finish Date 31st July 2021
Progress 100%
Task Status Complete
Task Status: On Schedule, Early Complete,Late, Future Task, Complete
Whilst we’ve completed 80% of the task it’s still late but our plan isn’t reflecting this. Similarly, if we reduce the progress to say 25% it shows as late but doesn’t give an accurate reflection of the progress made. I’d also like to report on completed tasks in terms of what was delivered early/on time/late but we’re struggling to get this in place.
Is there anyone who could help me?
Many Thanks
Dhan