SOLVED

MS Project, resource graph, show availability line in front of unit availability bars, how to?

Occasional Contributor

In the resource graph I am showing the "unit availability" as bars, and I checked the "show availability line", however the later hides behind the unit availability bars making it difficult to see it.

 

Can it be brought forefront?

Yann78_0-1662518975189.png

 

1 Reply
best response confirmed by Yann-78 (Occasional Contributor)
Solution
Yann-78,
I agree that it would be nice to see the availability line in front of the bars but unfortunately that option is not available. I suggest you submit a request via the Feedback channel (file > Feedback > "I have a suggestion").
John