Nov 04 2022 03:02 PM
Hi,
Hoping someone can help with this one.
Created a Master Project file to track multiple projects and when I insert the first Subproject ("Finance Department Audit Process"), the Master Project Duration is less than the Subproject summary.
Any suggestions on how I can reconcile this would be greatly appreciated.
Cheers!
Task Mode | Task Name | % Complete | Duration | Start | Finish |
Auto Scheduled | Master Project | 55% | 349 days? | 2022-01-11 | 2023-05-12 |
Auto Scheduled | Finance Department Audit Process | 55% | 354 days? | 2022-01-11 | 2023-05-12 |
Auto Scheduled | 22-Audit ABC | 47% | 180 days? | 2022-06-22 | 2023-02-23 |
Task Mode | Task Name | % Complete | Duration | Start | Finish |
Auto Scheduled | Production Audit Process | 55% | 259 days? | 2022-03-13 | 2023-03-02 |
Auto Scheduled | 22-Audit ABC-D | 55% | 259 days? | 2022-03-13 | 2023-03-02 |
Nov 04 2022 05:05 PM - edited Nov 05 2022 04:35 PM
KenPb,
Thanks for the picture but it doesn't give quite enough information. For example, what is the task ID for each of the tasks shown in your "screen shot"?
Other relevant information:
1. What is the Project calendar for the master?
2. What is the Project calendar for each subproject?
3. If calendars are different, what are the differences (e.g. working hours, working days, hours per day, etc.)?
4. In the master do you have the calculation option set to "on"?
5. Also in your Project options do you have "inserted projects to be calculated like summary tasks"?
John
Nov 09 2022 02:49 AM - edited Nov 09 2022 02:50 AM
@John-project Hi and thanks for the reply. The calendars for the master and sub projects are all standard M-F 40hr work week however in one of the sub projects there are a number of exceptions where a task start and completion date was on a non working day. I believe this might be the issue. Any recommendations to resolve?
Thanks, Ken
Nov 09 2022 06:12 AM
Nov 09 2022 10:23 AM
Hi and thanks for your patience. My project that I was working on was fairly advanced with a lot of content, so it was a bit difficult to get that info.
I however reproduced the issue in a simpler test project below:
The discrepancy occurred when, for SubProject ABC, I put the start, end completion date on Sunday (non-working day) where I introduced this exception.
The calendars for the Master and subprojects are all Standard (40hrs, M-F).
I hope this is enough info to help diagnose a resolution. Thanks, Ken
Task Mode | Task Name | % Complete | Duration | Start | Finish | ID |
Auto Scheduled | Master Project Test | 47% | 62 days? | 2022-09-23 | 2022-12-19 | 0 |
1 | ||||||
Auto Scheduled | SubProject ABC | 69% | 63 days | 2022-09-23 | 2022-12-19 | 2 |
Auto Scheduled | Define Scope | 100% | 21 days | 2022-09-23 | 2022-10-21 | 1 |
Auto Scheduled | Development | 100% | 5 days | 2022-10-24 | 2022-10-28 | 2 |
Auto Scheduled | Test | 100% | 1 day | 2022-10-30 | 2022-10-30 | 3 |
Auto Scheduled | Implement | 0% | 12 days | 2022-12-02 | 2022-12-19 | 4 |
3 | ||||||
Auto Scheduled | SubProject DEF | 0% | 29 days? | 2022-11-09 | 2022-12-19 | 4 |
Auto Scheduled | Define Scope | 0% | 8 days | 2022-11-09 | 2022-11-18 | 1 |
Auto Scheduled | Development | 0% | 15 days | 2022-11-21 | 2022-12-09 | 2 |
Auto Scheduled | Test | 0% | 1 day? | 2022-12-12 | 2022-12-12 | 3 |
Auto Scheduled | Implement | 0% | 5 days | 2022-12-13 | 2022-12-19 | 4 |
Nov 09 2022 12:48 PM
SolutionNov 09 2022 01:08 PM
@John-project Thank you so much for all the help. With the Master Project file summary line, I was hoping to show the Total number of days based on the dominant subproject (longest duration + exceptions) across all subprojects. Since I am not VBA savvy, I think I can manage it "manually" with your suggested custom text field. Once again, thanks for all your help in furthering my understand.
Best regards, Ken
Nov 09 2022 02:15 PM
Nov 09 2022 12:48 PM
Solution