Apr 26 2023 08:53 AM
Hello.
My team has MS Project for the Web - Plan 3. We are a PMO. Our PMO Team have licenses, but most of our stakeholders do not. We do want to give them access to our online project plans. We have gone through the "User Group" settings and made our stakeholders members of groups like "Project XYZ Visitors," "Project XYZ Members," etc.
But... when we provide a link to project plans, our stakeholders get error messages that say they cannot access or view (see below). These Users are not external. They all are internal to our org and have Office 365.
Simply making them members of "User Groups" within the PWA isn't enough. Any ideas are appreciated. We don't want to have to give everyone a MS Project license if they don't need one.
Apr 26 2023 10:55 AM - edited Apr 26 2023 11:05 AM
Hi Berto,
I am working as Project Online support engineer. Project for web for creating the plans only , users groups or creating the security groups is done in project online. Users will not get access by assigning them to security groups. License also required for PO. You can assign PLAN 1 license ( basic license ) ( less cost compared to plan 3 or plan 5 )to your stakeholders and assign Portfolio Viewers security groups. So that they will get access to PO.
Without license we can't be able to access Project.
Hope that can help you and open for any inputs, suggestions.
Apr 26 2023 10:55 AM
Apr 26 2023 01:10 PM - edited Apr 27 2023 07:13 AM
Update - I have confirmed that we have permissions mode. I've attached what I see when I look at my options re: Users...
I have read this page to understand how to add Users, but I can't find the navigation in MS Project Online.
This is what my landing page looks like. There is no icon here for adding Users. Any help is appreciated.
This is what my PWA settings page looks like...
And this is my Site Settings page...
Apr 29 2023 11:24 AM
Apr 29 2023 12:15 PM
May 01 2023 01:46 PM
@Dale Howard - Thank you for the information. I have the setting correct now.
Team members have been set up as "User can be assigned as a resource."
I believe I am clear on your comment, "All of your PWA users will need licenses, including your stakeholders."
What I want is to set up people as Guests. Our rationale for purchasing Project Online in part was because it is advertised as allowing non-licensed "Guests" viewing access to project plans.
I've tried to follow the steps in the article to no avail. It seems that I have set up someone as a Guest in Microsoft 365, not Project Online.
May 02 2023 05:17 AM
May 05 2023 09:57 AM - edited May 05 2023 09:58 AM
Project Online. I'm basing that on this view...
May 05 2023 11:40 AM
Dec 16 2023 12:36 AM