SOLVED

MS Project Online Desktop Client - Showing Work for Each Resource per Task

New Contributor

Hi All,

 

Does anyone know of a way to show the level of effort (or work) of individual resources per task? Specifically when a task has multiple resources assigned?

 

Ideally I'd like to be able to generate a table as depicted below

 

Task

LoE for Resource A

LoE for Resource B

LoE for Resource C

Develop methodology

10hrs

25hrs

3hrs

Develop tool

40hrs

80hrs

15hrs

Use tool

8hrs

40hrs

5hrs

 

Any help would be greatly appreciated.

 

Kind regards,

 

Christian

3 Replies
best response confirmed by ChristianMNP (New Contributor)
Solution
Christian --

The Task Usage view is the closest that you will get to your reporting requirements. The Work column will show the total amount of work applied to each resource that is assigned to each task. Hope this helps.
Hi Dale,

Thanks for the response, its not a fully automated way of generating a report but I'll take whatever ends up saving me time, which this definitely does :)

Kind regards,

Christian
ChristianMNP --

You are more than welcome for the help, my friend! :)