MS Project Calculating Duration Incorrectly

%3CLINGO-SUB%20id%3D%22lingo-sub-3411428%22%20slang%3D%22en-US%22%3EMS%20Project%20Calculating%20Duration%20Incorrectly%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3411428%22%20slang%3D%22en-US%22%3E%3CP%3EWhen%20I%20set%20a%20fixed%20duration%20task%20to%20start%20on%205%2F25%20and%20finish%20on%206%2F7%2C%20this%20is%20a%20duration%20of%2010%20days.%20MS%20Project%20for%20some%20reason%20however%2C%20is%20displaying%20a%20duration%20of%2012%20days.%20This%20is%20incorrect.%20I%20don't'%20understand%20why%20its%20doing%20this.%20If%20I%20manually%20change%20the%20duration%20field%20to%2010%20days%2C%20then%20project%20changes%20the%20finish%20date%20to%206%2F6%2C%20which%20is%20still%20not%20correct%20because%20working%20days%20from%205%2F25%20to%206%2F6%20would%20be%208%20days.%20I%20have%20May%2030th%20scheduled%20as%20a%20non-working%20day%20for%20memorial%20day.%20See%20screenshot.%26nbsp%3B%20I'm%20not%20sure%20if%20it%20has%20anything%20to%20do%20with%20the%20options%20I%20have%20set%20for%20the%20project%20which%20is%206%20hours%20per%20day%2C%2030%20hours%20per%20week%20to%20account%20for%20the%20reality%20that%20its%20not%20realistic%20for%20someone%20to%20be%20able%20to%20dedicate%20a%20full%208%20hour%20day%20to%20project%20work.%3C%2FP%3E%3CP%3E%26nbsp%3B%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20image-alt%3D%22Screenshot%202022-05-22%20113018.jpg%22%20style%3D%22width%3A%20400px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F374025i2EB2208D1ADEB282%2Fimage-size%2Fmedium%3Fv%3Dv2%26amp%3Bpx%3D400%22%20role%3D%22button%22%20title%3D%22Screenshot%202022-05-22%20113018.jpg%22%20alt%3D%22Screenshot%202022-05-22%20113018.jpg%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-3411428%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3411659%22%20slang%3D%22en-US%22%3ERe%3A%20MS%20Project%20Calculating%20Duration%20Incorrectly%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3411659%22%20slang%3D%22en-US%22%3EJohn%20Bacon%2C%3CBR%20%2F%3EI'm%20guessing%20you%20did%20not%20change%20the%20working%20calendar%20to%20reflect%20the%206%20hour%20work%20day.%20By%20default%2C%20each%20work%20day%20is%208%20hours%20(8%3A00%20AM%20to%2012%3A00%20PM%20and%201%3A00%20PM%20to%205%3A00%20PM).%20The%20number%20of%20default%20days%20from%205%2F25%2F22%20through%206%2F7%2F22%2C%20including%20the%20non-working%20memorial%20day%2C%20is%209.%20So%209%20of%20the%20default%208%20hour%20working%20days%20equals%2072%20hours.%20However%2C%20you%20have%20re-defined%20a%20%22day%22%20as%206%20hours%20so%2072%20divided%20by%206%20equals%2C%20wait%20for%20it%2C%2012%20%22days%22.%3CBR%20%2F%3E%3CBR%20%2F%3EThe%20fact%20that%20resources%20may%20only%20be%2075%25%20efficient%20is%20not%20relevant%20for%20Project's%20scheduling%20calculation.%20That's%20something%20you%20will%20have%20to%20take%20into%20account%20when%20you%20estimate%20task%20durations%20and%20assign%20resources.%3CBR%20%2F%3E%3CBR%20%2F%3EHope%20this%20helps.%3CBR%20%2F%3EJohn%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3411720%22%20slang%3D%22en-US%22%3ERe%3A%20MS%20Project%20Calculating%20Duration%20Incorrectly%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3411720%22%20slang%3D%22en-US%22%3EYes.%20I%20checked%20and%20I%20did%20leave%20the%20project%20calendar%20work%20times%20from%208-12%20and%201-5.%20I%20thought%20by%20changing%20working%20hours%20in%20project%20schedule%20options%20to%206%2C%20project%20would%20do%20its%20calculations%20accordingly%20assuming%20a%20resource%20assigned%20at%20100%25%20is%20still%20only%206%20hours%20per%20day.%20So%20what%20you%20are%20suggesting%20is%20that%20I%20change%20the%20working%20hours%20per%20day%20back%20to%208%2C%20hours%20per%20week%20back%20to%2040.%20Leave%20the%20project%20calendar%20working%20time%20as%208-12%20and%201-5%2C%20but%20add%20resources%20with%20Max%20Units%20of%2075%25%20to%20account%20for%20administrative%20non-project%20related%20tasks%20performed%20during%20the%20day%2C%20and%20this%20should%20fix%20my%20calculation%20issue%3F%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3411727%22%20slang%3D%22en-US%22%3ERe%3A%20MS%20Project%20Calculating%20Duration%20Incorrectly%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3411727%22%20slang%3D%22en-US%22%3E%3CP%3EOr%2C%20if%20I%20just%20change%20the%20project%20calendar%20working%20times%20to%208-12%20and%201-3.%26nbsp%3B%20Will%20that%20also%20resolve%20my%20duration%2C%20start%20date%2C%20finish%20date%20discrepancy%3F%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3411792%22%20slang%3D%22en-US%22%3ERe%3A%20MS%20Project%20Calculating%20Duration%20Incorrectly%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3411792%22%20slang%3D%22en-US%22%3EJBLT83%2C%3CBR%20%2F%3EWell%20my%20question%20for%20you%20is%2C%20what%20are%20your%20company%20working%20hours%3F%20Are%20they%20normal%208%20hour%20working%20days%20or%20are%20they%206%20hour%20working%20days%3F%20If%20they%20are%208%20hour%20working%20days%2C%20then%20don't%20mess%20with%20the%20working%20times%2C%20unless%20you%20need%20to%20change%20them%20to%20say%2C%207%3A00%20AM%20to%2011%3A00%20AM%20and%2011%3A30%20AM%20to%203%3A30%20PM%2C%20or%20similar.%3CBR%20%2F%3E%3CBR%20%2F%3EIf%20a%20resource%20is%20a%20full%20time%20employee%20then%20their%20Max%20Units%20(Resource%20Sheet)%20should%20be%20100%25.%20The%20amount%20of%20time%20they%20are%20expected%20to%20spend%20on%20any%20given%20task%20is%20determined%20by%20the%20assignment%20units.%20So%20if%20a%20resource%20has%20other%20tasks%2C%20allocate%20their%20assignment%20across%20all%20those%20tasks.%20Project%20will%20warn%20you%20if%20a%20resource%20is%20overallocated%20(i.e.%20assignment%20level%20over%20a%20defined%20period%20exceeds%20their%20Max%20Units%20value).%20That%20defined%20level%20can%20be%20set%20via%2C%20Resource%20%26gt%3B%20Level%20group%20%26gt%3B%20Leveling%20options.%3CBR%20%2F%3E%3CBR%20%2F%3EWhen%20it%20comes%20to%20resource%20efficiency%20the%20best%20way%20to%20handle%20that%20is%20to%20allow%20extra%20work%20hours%20for%20a%20task.%20Let's%20say%20a%20task%20should%20normally%20take%208%20hours%20to%20complete%20but%20because%20human%20resources%20are%20normally%20not%20100%25%20efficient%2C%20you%20might%20enter%20a%20work%20content%20of%2010%20hours%20(80%25).%20However%2C%20you'll%20likely%20find%20that%20trying%20to%20work%20a%20project%20at%20that%20fine%20a%20detail%20is%20more%20effort%20than%20its%20worth%20(i.e.%20resource%20efficiency%20is%20a%20very%20small%2C%20likely%20insignificant%2C%20part%20of%20the%20issues%20the%20project%20manager%20faces%20during%20execution%20of%20a%20plan).%3CBR%20%2F%3E%3CBR%20%2F%3EJohn%3C%2FLINGO-BODY%3E
Contributor

When I set a fixed duration task to start on 5/25 and finish on 6/7, this is a duration of 10 days. MS Project for some reason however, is displaying a duration of 12 days. This is incorrect. I don't' understand why its doing this. If I manually change the duration field to 10 days, then project changes the finish date to 6/6, which is still not correct because working days from 5/25 to 6/6 would be 8 days. I have May 30th scheduled as a non-working day for memorial day. See screenshot.  I'm not sure if it has anything to do with the options I have set for the project which is 6 hours per day, 30 hours per week to account for the reality that its not realistic for someone to be able to dedicate a full 8 hour day to project work.

 Screenshot 2022-05-22 113018.jpg

4 Replies
best response confirmed by JBLT83 (Contributor)
Solution
John Bacon,
I'm guessing you did not change the working calendar to reflect the 6 hour work day. By default, each work day is 8 hours (8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM). The number of default days from 5/25/22 through 6/7/22, including the non-working memorial day, is 9. So 9 of the default 8 hour working days equals 72 hours. However, you have re-defined a "day" as 6 hours so 72 divided by 6 equals, wait for it, 12 "days".

The fact that resources may only be 75% efficient is not relevant for Project's scheduling calculation. That's something you will have to take into account when you estimate task durations and assign resources.

Hope this helps.
John
Yes. I checked and I did leave the project calendar work times from 8-12 and 1-5. I thought by changing working hours in project schedule options to 6, project would do its calculations accordingly assuming a resource assigned at 100% is still only 6 hours per day. So what you are suggesting is that I change the working hours per day back to 8, hours per week back to 40. Leave the project calendar working time as 8-12 and 1-5, but add resources with Max Units of 75% to account for administrative non-project related tasks performed during the day, and this should fix my calculation issue?

Or, if I just change the project calendar working times to 8-12 and 1-3.  Will that also resolve my duration, start date, finish date discrepancy?

JBLT83,
Well my question for you is, what are your company working hours? Are they normal 8 hour working days or are they 6 hour working days? If they are 8 hour working days, then don't mess with the working times, unless you need to change them to say, 7:00 AM to 11:00 AM and 11:30 AM to 3:30 PM, or similar.

If a resource is a full time employee then their Max Units (Resource Sheet) should be 100%. The amount of time they are expected to spend on any given task is determined by the assignment units. So if a resource has other tasks, allocate their assignment across all those tasks. Project will warn you if a resource is overallocated (i.e. assignment level over a defined period exceeds their Max Units value). That defined level can be set via, Resource > Level group > Leveling options.

When it comes to resource efficiency the best way to handle that is to allow extra work hours for a task. Let's say a task should normally take 8 hours to complete but because human resources are normally not 100% efficient, you might enter a work content of 10 hours (80%). However, you'll likely find that trying to work a project at that fine a detail is more effort than its worth (i.e. resource efficiency is a very small, likely insignificant, part of the issues the project manager faces during execution of a plan).

John