Sep 25 2023 06:05 PM
We recently migrated to MS Project 2019. We've noticed that when we replace a resource on a task using Assign Resources, the original resource's baseline work is cleared or reduced. On our previous Project the new resource would retain all the replaced resource's baseline work.
Is there an option somewhere to remove the clearing of a baseline from a task resource during a replace? Or does one of the CU's fix this issue?
Sep 25 2023 06:50 PM - edited Sep 25 2023 06:56 PM
RCook1959,
First of all, no, there is no option to clear the baseline when a resource is changed. Baseline fields are static, it takes direct user action to set a baseline, change a baseline or clear a baseline.
How exactly are you replacing the resource? Do you remove the original resource before assigned the new resource? Do both resource have the same Base Calendar and Max Units and are they the same type (e.g. Work)?
What is your version and build? The latest is version 2308 (build 16731.20234 CTR).
John
Sep 26 2023 05:09 AM
I normally use the "Assign Resources" dialog to replace resources. There are a couple of other ways but that's the primary method.
The more I think about the problem, the more I think the process was changed by Microsoft because the new resource was not present during baseline. As such, a new resource should not contain the baseline originally laid in during planning.
I would have liked for the process to keep the original resource with their baseline timephasing intact and zero out the remaining work. The new resource would be added with the remaining work and no baseline. There is a way around this but it takes longer to do as you can't just replace the existing resource and feel everything is good to go..
Sep 26 2023 09:35 AM
Sep 26 2023 09:44 AM