Migration from 2013->2019 - Project site selection not possible

%3CLINGO-SUB%20id%3D%22lingo-sub-2569851%22%20slang%3D%22en-US%22%3EMigration%20from%202013-%26gt%3B2019%20-%20Project%20site%20selection%20not%20possible%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2569851%22%20slang%3D%22en-US%22%3E%3CP%3EHello%2C%3C%2FP%3E%3CP%3Eafter%20migrating%20from%20Project%20Server%202013%20to%20Project%20Server%202019%20I%20found%20this%20strange%20behavior%20for%20Enterprise%20Project%20Types%3A%3C%2FP%3E%3CP%3EThe%20dropdown%20field%20for%20selecting%20the%20Project%20Site%20Template%20language%20and%20Template%20is%20not%20populated%20-%20not%20with%20the%20template%20used%20in%20Project%20Server%202013%20(which%20is%20not%20working)%20and%20not%20with%20the%20Standard%20Project%20Site%20or%20a%20newly%20created%20Project%20Site%20Template.%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20image-alt%3D%222021-07-19%2016_59_34-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20style%3D%22width%3A%20873px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F297342i564A3D0D24CC4F4A%2Fimage-size%2Flarge%3Fv%3Dv2%26amp%3Bpx%3D999%22%20role%3D%22button%22%20title%3D%222021-07-19%2016_59_34-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20alt%3D%222021-07-19%2016_59_34-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3CP%3EThe%20templates%20(old%20and%20new)%20can%20be%20found%20as%20activated%20in%20the%20Solutions%20Gallery%20and%20I%20can%20generate%20a%20new%20Subsite%20using%20the%20standard%20Project%20Site%20template%20as%20well%20as%20using%20the%20new%20template.%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20image-alt%3D%222021-07-19%2017_06_43-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20style%3D%22width%3A%20999px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F297344iD969F57AC8FF29FF%2Fimage-size%2Flarge%3Fv%3Dv2%26amp%3Bpx%3D999%22%20role%3D%22button%22%20title%3D%222021-07-19%2017_06_43-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20alt%3D%222021-07-19%2017_06_43-mRemoteNG%20-%20confCons.xml%20-%20SERV-T-PRO21%20-%20APP.png%22%20%2F%3E%3C%2FSPAN%3EAny%20ideas%3F%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-2569920%22%20slang%3D%22en-US%22%3ERe%3A%20Migration%20from%202013-%26gt%3B2019%20-%20Project%20site%20selection%20not%20possible%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2569920%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F369936%22%20target%3D%22_blank%22%3E%40TamaraF%3C%2FA%3E%26nbsp%3B%2C%3C%2FP%3E%0A%3CP%3ETry%20the%20following%3A%3C%2FP%3E%0A%3CUL%3E%0A%3CLI%3EArrange%20a%20system%20outage%3CUL%3E%0A%3CLI%3EAssuming%20the%20system%20is%20live%20etc.%3C%2FLI%3E%0A%3C%2FUL%3E%0A%3C%2FLI%3E%0A%3CLI%3EBackup%20the%20content%20database%20where%20the%20PWA%20site%20collection%20is%20hosted%3CUL%3E%0A%3CLI%3EJust%20in%20case%20something%20goes%20wrong%2C%20you%20can%20restore%20the%20database%20backup%3C%2FLI%3E%0A%3C%2FUL%3E%0A%3C%2FLI%3E%0A%3CLI%3ERun%20the%20following%20PowerShell%20command%3A%20Disable-SPFeature%20pwasite%20-Url%20%3CURL%3E%3C%2FURL%3E%3C%2FLI%3E%0A%3CLI%3ERun%20the%20following%20PowerShell%20command%3A%20Enable-SPFeature%20pwasite%20-Url%20%3CURL%3E%3C%2FURL%3E%3C%2FLI%3E%0A%3C%2FUL%3E%0A%3CP%3ESee%20if%20that%20resolves%20the%20issue.%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

Hello,

after migrating from Project Server 2013 to Project Server 2019 I found this strange behavior for Enterprise Project Types:

The dropdown field for selecting the Project Site Template language and Template is not populated - not with the template used in Project Server 2013 (which is not working) and not with the Standard Project Site or a newly created Project Site Template.

2021-07-19 16_59_34-mRemoteNG - confCons.xml - SERV-T-PRO21 - APP.png

The templates (old and new) can be found as activated in the Solutions Gallery and I can generate a new Subsite using the standard Project Site template as well as using the new template.

2021-07-19 17_06_43-mRemoteNG - confCons.xml - SERV-T-PRO21 - APP.pngAny ideas?

2 Replies
best response confirmed by TamaraF (Occasional Contributor)
Solution

Hello @TamaraF ,

Try the following:

  • Arrange a system outage
    • Assuming the system is live etc.
  • Backup the content database where the PWA site collection is hosted
    • Just in case something goes wrong, you can restore the database backup
  • Run the following PowerShell command: Disable-SPFeature pwasite -Url <URL>
  • Run the following PowerShell command: Enable-SPFeature pwasite -Url <URL>

See if that resolves the issue.

Paul

Thanks, Paul. That did the trick - the Project Site templates are now back in the dropdown!