SOLVED

Migrate from Project Server 2013 to Project Online

Copper Contributor

Hello,

i'm going to migrate project server from 2013 to project online, i found resources for how to move projects to Project online but i didn't find any resources for how to move (project Calendar, risks & issues Lists, reports and custom enterprise field), so if anyone has the same experience please advise me.

thanks in advance,

1 Reply
best response confirmed by Adullah_Ismail (Copper Contributor)
Solution

Hello @Adullah_Ismail 

For a full migration - look for 3rd party tools such as Fluentpro and one of the SharePoint migration tools.

Paul