Hello,
I am wondering if anyone has a suggestion on how to go about copying the default environment to a new production environment.
I had a situation this week where a user deleted a few project records and the only way to recover them was to restore to a backup however, there is no ability to do this on the default environment. Now I am looking for a way to convert all the projects, approx 100, over to a new environment where ill re deploy the project accelerator app but will have to ability to recover deleted projects or restore to a backup.
Thank you for your feedback.
Josh
Apr 29 2021 11:50 AM
SolutionHello @Dribblej ,
You could export out the projects using this process: https://docs.microsoft.com/en-us/project-for-the-web/export-user-data-from-project-for-the-web then import using: https://techcommunity.microsoft.com/t5/project-blog/import-project-desktop-files-to-project-for-the-...
I've never tried this but see if this is an option. I'm not sure in the MPP file generated using the export and be imported etc.
Paul
May 07 2021 09:55 AM
Nov 01 2023 01:23 AM
Apr 29 2021 11:50 AM
SolutionHello @Dribblej ,
You could export out the projects using this process: https://docs.microsoft.com/en-us/project-for-the-web/export-user-data-from-project-for-the-web then import using: https://techcommunity.microsoft.com/t5/project-blog/import-project-desktop-files-to-project-for-the-...
I've never tried this but see if this is an option. I'm not sure in the MPP file generated using the export and be imported etc.
Paul