Apr 15 2020 08:13 AM
Can anyone inform me how to migrate a project created in Project Plan 1 (SharePoint Online Plan) into Project Plan 3 (Project Web App)? Or isn't that possible?
It seems I cannot download or copy/paste a project from Plan 1 to Plan 3 at all….
Do I have to enter a complete new project in Project Plan 3?
Apr 15 2020 08:32 AM
Hello @annemarl1,
Please can you confirm where the plan currently exists? It is a Project for the web type project? It is like this example here: https://support.office.com/en-gb/article/get-started-with-project-for-the-web-50bf3e29-0f0d-4b7a-9d2...
Paul
Apr 15 2020 09:19 AM
Hi @Paul Mather, actually I have no idea :)
Project 1 is on https://project.microsoft.com/etcetera en Project 3 is on "companyname".SharePoint.com.
Issue is that I've figured out that Project 3 has more features (like saving as pdf) and Project 1 not.
I would like to do 2 things:
1) import my already entered file in Project 1 in Project 3 (so I don't have to type over all the tasks)
2) new file in Project 3 save/export somewhere else (e.g. Onedrive as a file or on a stick)
Also, what is the difference between "companyname".SharePoint.com and "companyname"-my.SharePoint.com??
Apr 15 2020 09:26 AM
Apr 15 2020 10:10 AM
Hello @annemarl1 ,
Unfortunately there is no way to migrate / export a project plan from Project for the web into Project Online Project Web App.
Paul
Apr 15 2020 10:15 AM
Apr 16 2020 01:44 AM
Hello @annemarl1,
A Project for the web project can't be exported to a file.
company.sharepoint.com is the main tenant, company-my.sharepoint.com is the personal sites like the classic My Sites in previous versions of SharePoint - this is where your personal OneDrive is etc.
Paul
Jun 24 2020 05:10 PM
Hello,
I'd like to confirm my understanding of Project Plan 1 vs. Project Plan 3.
Please confirm.
Thanks, Mike
Jun 25 2020 01:07 AM
Hi @MikeP8888 ,
Unfortunately there is no way out of the box to migrate a project from Project for the Web to Project Online.
Paul
Sep 29 2023 12:38 AM
Dear Paul
the last answer in this topic is from June 2020. Is there anything new? I have exactly the same issue as MikeP8888. Entered a lot of data in Plan 1 and realised the very limited capabilities of this version and now would like to use plan 3. I guess still no Out of the box solution, but is there a circumvention? Best regards and thank you! Peter
Sep 29 2023 12:50 AM
Hello @Peter_Roethlisberger - still the same answer unfortunately.
Sep 29 2023 01:04 AM
SolutionSep 29 2023 01:04 AM
Solution