Hi,
We need some help where there is % complete discrepancy while importing the Microsoft Project schedule into Primavera P6.
We did some testing on our side and identified some issues with the actual duration capture in Microsoft Project. Seems it's different with Primavera P6.
We need to ensure Planned Vs Actual should match between Primavera P6 and Microsoft Project.
Kindly check the attached document and the Microsoft project schedule which explains the issue we are facing right now.
Thanks.
Arief
Dec 01 2021 09:25 AM
Dec 02 2021 11:15 PM
Result: When there is no delay in the activity/task, both MSP and P6 give almost the same value output for the actual duration and the percent complete.
Result: When there is delay in the activity/task, P6 includes the delay duration to the actual duration, whereas MSP doesn't include the delay duration to the actual duration, instead showing it in the Finish variance column.
MSP Schedule:
P6 Schedule:
Dec 03 2021 05:25 AM
Dec 07 2021 12:02 AM
Dec 07 2021 02:09 PM