Microsoft Project Professional 2019 - Agile functionality

Copper Contributor

Need guidance as I'd like to have the ability to do sprint plans in project. 

I did some research and found that to work with Agile, I must have the right release(s) as agile features work only with MS Project Online Desktop Client.  Not sure what version or type of Project do I need in order to have this functionality available. Shall I need Microsoft Project Professional 2019 or an online subscription instead?

 

Appreciate the help!

1 Reply

Hello @Anita_1478 ,

The Agile / Task boards capability is only in the Project Online Desktop Client, see the link below for details:

https://support.microsoft.com/en-us/office/use-task-boards-in-microsoft-project-online-desktop-clien...

Paul