SOLVED

Microsoft Project Online (PWA) some work resources missing Capacity

%3CLINGO-SUB%20id%3D%22lingo-sub-2243051%22%20slang%3D%22en-US%22%3EMicrosoft%20Project%20Online%20(PWA)%20some%20work%20resources%20missing%20Capacity%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2243051%22%20slang%3D%22en-US%22%3E%3CP%3EHI%2C%3C%2FP%3E%3CP%3Ein%20our%20PWA%20implementation%20we%20have%20some%20resources%20that%20appear%20with%20blank%20Capacity%20although%20they%20have%20max.%20units%20set%20to%20100%25%20and%20have%20project%20assignments.%20As%20this%20only%20happens%20to%20some%20resources%20it%20seems%20to%20be%20a%20bug%20%3F)%20as%20I%20can't%20find%20anything%20different%20between%20the%20%22null%22%20Capacity%20resources%20and%20others.%3C%2FP%3E%3CP%3EHas%20this%20happened%20to%20anyone%20and%20if%20so%20how%20did%20you%20solve%3F!%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EThanks%20in%20advance%2C%3C%2FP%3E%3CP%3ERosie%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-2243291%22%20slang%3D%22en-US%22%3ERe%3A%20Microsoft%20Project%20Online%20(PWA)%20some%20work%20resources%20missing%20Capacity%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2243291%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F134086%22%20target%3D%22_blank%22%3E%40Rosalia%20Dias%3C%2FA%3E%26nbsp%3B%2C%3C%2FP%3E%0A%3CP%3EAre%20the%20resources%20showing%20as%20null%20capacity%20part%20of%20a%20Team%20Assignment%20Pool%3F%20If%20so%2C%20this%20is%20expected%20as%20their%20capacity%20contributes%20to%20the%20overall%20Team%20capacity.%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Contributor

HI,

in our PWA implementation we have some resources that appear with blank Capacity although they have max. units set to 100% and have project assignments. As this only happens to some resources it seems to be a bug ?) as I can't find anything different between the "null" Capacity resources and others.

Has this happened to anyone and if so how did you solve?!

 

Thanks in advance,

Rosie

2 Replies
best response confirmed by Rosalia Dias (Occasional Contributor)
Solution

Hello @Rosalia Dias ,

Are the resources showing as null capacity part of a Team Assignment Pool? If so, this is expected as their capacity contributes to the overall Team capacity.

Paul

@Paul Mather yes they are! in that case I must remove from Team Assignment pool - I will do that. Thanks!